A key project team member had an accident and will be in the hospital for at least two months. The backlog items the team member was working on have been delayed since the team member was the only person who knew how to complete them.
What could the project manager have done to avoid this situation?
victory108
6 months, 3 weeks agoKim222
9 months, 1 week agoompk
1 year agonqbaotd
11 months, 3 weeks ago517f9da
1 year ago[Removed]
1 year, 3 months agoTrytrio
1 year, 4 months agodinhnghia
1 year, 4 months agoAbdelmonm
1 year, 5 months agochlaithem
1 year, 5 months agoodylec
1 year, 5 months agoElla008
1 year, 5 months ago6thEditionAndy
1 year, 6 months agoJaya12
1 year, 6 months agoHanbyul
1 year, 6 months agocb4a6c4
1 year, 6 months agoprinceviper
1 year, 6 months ago