A company is going through a large cost-cutting initiative. Senior management requests a report on the work remaining for outstanding projects.

Which tool should the project manager use for this purpose?

  • A. Forecast estimation
  • B. Earned value (EV)
  • C. Cumulative flow diagram
  • D. Burndown chart
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
STAR666
3 months ago
Selected Answer: A
In the context of cost-cutting initiatives, senior management is likely looking for a report that can provide an estimate of how much work remains and what the financial implications are for outstanding projects. Forecast estimation is the best tool for this purpose, as it provides an estimated prediction of future work based on current project performance, allowing the project manager to forecast remaining work and associated costs. Forecast estimation typically uses data such as remaining work and current performance trends (like velocity or work completed over time) to predict future outcomes.
upvoted 1 times
...
victory108
5 months, 3 weeks ago
Selected Answer: D
D. Burndown chart
upvoted 1 times
...
517f9da
1 year ago
Selected Answer: D
D. Burndown chart A burndown chart is a graphical representation that shows the remaining work versus time. It helps project managers and stakeholders understand the amount of work left in a project and whether the project is on track to complete on time.
upvoted 2 times
...
[Removed]
1 year, 2 months ago
Selected Answer: D
D - This chart is a graphical representation of the work remaining in a timebox or the work completed toward the release of a product or project deliverable
upvoted 2 times
...
SAJSAJ
1 year, 2 months ago
i'll go with A
upvoted 1 times
...
hoomz
1 year, 2 months ago
Selected Answer: D
Simply "work remaining" no need for deep analysis with EV.
upvoted 2 times
...
Trytrio
1 year, 3 months ago
Selected Answer: B
Earned Value (EV) is a project management technique that combines cost, schedule, and work performance data to assess project progress and forecast future performance. It provides a clear picture of how much work has been completed in relation to the planned work and how much work remains to be done. EV allows senior management to assess project performance, identify variances, and make informed decisions regarding cost-cutting initiatives and resource allocation for outstanding projects.
upvoted 2 times
...
dapper18
1 year, 4 months ago
A Burndown Chart could also be a valuable tool for tracking and reporting the progress of outstanding projects during a cost-cutting initiative. A Burndown Chart visually represents the work completed (or "burned down") over time against the total work required. It helps in tracking the project's trajectory and predicting when the work will likely be completed.
upvoted 1 times
...
6thEditionAndy
1 year, 5 months ago
Selected Answer: A
Actually, upon rereading the question. Management wants to cut costs. A burndown chart gives no information on costs. The forecast estimation shows however, how much we still need to spend for the project.
upvoted 2 times
...
6thEditionAndy
1 year, 5 months ago
Selected Answer: D
Burndown Chart shows what has been done and what still needs to be done, thus gives the most comprehensive overview
upvoted 2 times
...
cb4a6c4
1 year, 5 months ago
Selected Answer: D
Its D. Work completed till date and what is still pending.
upvoted 2 times
...
Jaya12
1 year, 5 months ago
Selected Answer: D
The burndown chart offers a clear and concise representation of the remaining work and its anticipated completion, making it an appropriate choice for this scenario.
upvoted 1 times
...
cb4a6c4
1 year, 5 months ago
Selected Answer: B
Earned Value - Shows the cost involved to complete the project and the current status as well (AC).
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago