In the context of cost-cutting initiatives, senior management is likely looking for a report that can provide an estimate of how much work remains and what the financial implications are for outstanding projects. Forecast estimation is the best tool for this purpose, as it provides an estimated prediction of future work based on current project performance, allowing the project manager to forecast remaining work and associated costs.
Forecast estimation typically uses data such as remaining work and current performance trends (like velocity or work completed over time) to predict future outcomes.
D. Burndown chart
A burndown chart is a graphical representation that shows the remaining work versus time. It helps project managers and stakeholders understand the amount of work left in a project and whether the project is on track to complete on time.
D - This chart is a graphical representation of the work remaining in a timebox or the work completed toward the release of a product or project deliverable
Earned Value (EV) is a project management technique that combines cost, schedule, and work performance data to assess project progress and forecast future performance. It provides a clear picture of how much work has been completed in relation to the planned work and how much work remains to be done. EV allows senior management to assess project performance, identify variances, and make informed decisions regarding cost-cutting initiatives and resource allocation for outstanding projects.
A Burndown Chart could also be a valuable tool for tracking and reporting the progress of outstanding projects during a cost-cutting initiative. A Burndown Chart visually represents the work completed (or "burned down") over time against the total work required. It helps in tracking the project's trajectory and predicting when the work will likely be completed.
Actually, upon rereading the question. Management wants to cut costs. A burndown chart gives no information on costs. The forecast estimation shows however, how much we still need to spend for the project.
The burndown chart offers a clear and concise representation of the remaining work and its anticipated completion, making it an appropriate choice for this scenario.
Earned Value - Shows the cost involved to complete the project and the current status as well (AC).
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
STAR666
3 months agovictory108
5 months, 3 weeks ago517f9da
1 year ago[Removed]
1 year, 2 months agoSAJSAJ
1 year, 2 months agohoomz
1 year, 2 months agoTrytrio
1 year, 3 months agodapper18
1 year, 4 months ago6thEditionAndy
1 year, 5 months ago6thEditionAndy
1 year, 5 months agocb4a6c4
1 year, 5 months agoJaya12
1 year, 5 months agocb4a6c4
1 year, 5 months ago