A project manager is working on a global project. One team member is from a different country and is unable to attend project meetings on a regular basis. Because of this, other team members have started questioning the need for the project meeting. This issue is affecting the time line deliverable and quality parameters.

What should the project manager do to manage the project deliverables?

  • A. Define the rules for the project meeting.
  • B. Make it mandatory for all members to attend all project meetings.
  • C. Make it mandatory for all members to discuss their work at project meetings.
  • D. Define the agenda for the project meeting.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
6b0d17c
3 days, 18 hours ago
Selected Answer: A
Defining rules to overcome challenges of a dispersed team
upvoted 1 times
...
trungtd
2 weeks, 6 days ago
Selected Answer: A
Define meeting ground rules
upvoted 1 times
...
SukantaLearn
1 month, 3 weeks ago
Selected Answer: A
Define rules
upvoted 1 times
...
Amirov
9 months, 2 weeks ago
I'm more into option D, this approach allows for flexibility. If the team member cannot attend every meeting, they can prioritize joining during discussions that require their expertise, in this case: timeline deliverable and quality parameters, which can help alleviate any feelings of exclusion or disengagement.
upvoted 2 times
...
victory108
9 months, 3 weeks ago
Selected Answer: A
A. Define the rules for the project meeting
upvoted 1 times
...
tonybuivannghia
1 year ago
Selected Answer: D
I think other members don't know about the purposes of meeting, so agenda is a necessary tool that allows they understand and focus on the main content. So D is correct.
upvoted 2 times
...
Trytrio
1 year, 6 months ago
Selected Answer: D
Since he cannot join all the time an agenda would help to decide in which meetings he needs to be in. D is correct.
upvoted 2 times
...
KennyMuffins
1 year, 6 months ago
Selected Answer: D
Defining Agenda of meeting is important as other team members are questioning the need for project meeting. The one team member not being able to attend , could be of some valid reason , but not have impact to the other team members attending the meeting as well.
upvoted 3 times
...
Davard
1 year, 6 months ago
Selected Answer: D
Defining rules for the project meeting (option A) is important, but defining the agenda specifically addresses the issue of managing project deliverables by ensuring that meetings remain focused and productive despite the attendance challenges.
upvoted 2 times
...
xcjxcj
1 year, 7 months ago
Selected Answer: A
D. Agenda does not work on 1st member. He did not attend because time difference or environmental factors. A. works for him.
upvoted 2 times
...
jtr393
1 year, 7 months ago
Selected Answer: A
Defining rules for the project meeting aids with setting expectations, establishing structure, and ensures that the all the meetings are effective. It allows the project manager to address any concerns about attendance and other issues, which will help manage project deliverables efficiently.
upvoted 2 times
...
Abdelmonm
1 year, 7 months ago
Selected Answer: A
n this situation, the project manager should consider defining the rules for the project meeting and establishing an agenda. This can help address the challenges posed by the team member from a different country who is unable to attend meetings regularly. By defining the rules and agenda, the project manager can ensure that key discussions and decisions take place during the meetings, even if not all team members can attend every session.
upvoted 2 times
...
psvexam
1 year, 7 months ago
Ans A Define rules so applies to all
upvoted 1 times
...
6thEditionAndy
1 year, 8 months ago
Selected Answer: D
The issue is not that a remote person csnt always join, the issue is that others now that its okay to slack off in the meeting. We need to address this by adding meaning to the meeting. We can do this by explaining the purpose using an Agenda
upvoted 4 times
xcjxcj
1 year, 7 months ago
Purpose defined, you hope it works. the remote person still cannot join, because various reasons, then?
upvoted 1 times
...
...
loscoe
1 year, 8 months ago
Selected Answer: A
Team is questioning need because of behaviour of the non-attending resource, not because there's no agenda.
upvoted 1 times
...
Jaya12
1 year, 8 months ago
Selected Answer: D
Defining a clear agenda for project meetings is crucial as it guides discussions toward essential project aspects and objectives. While defining meeting rules (option A) is important, a well-defined agenda ensures that discussions remain focused on critical project topics, facilitating productive meetings even in the absence of certain team members.
upvoted 3 times
xcjxcj
1 year, 7 months ago
The problem is team members follow the 1st guy, now you give up the 1st guy?
upvoted 1 times
...
...
Hanbyul
1 year, 8 months ago
Selected Answer: A
A. Define the rules for the project meeting.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...