The project manager received a claim from the client because the outcome delivered is not working properly. The project manager investigated the cause and realized that this deliverable was outsourced to an external provider, and was not made aware.
What primary tool would have helped the project manager identify this situation?
Abhisk127
1 month, 2 weeks agoSukantaLearn
1 month, 2 weeks agovictory108
8 months, 3 weeks agoKim222
11 months, 2 weeks agoompk
1 year, 2 months ago517f9da
1 year, 2 months agoKennyMuffins
1 year, 5 months agohoomz
1 year, 5 months agoAbdelmonm
1 year, 6 months agoAntoFE
1 year, 7 months agoAntoFE
1 year, 7 months agoAntoFE
1 year, 7 months agoSamtx99
1 year, 7 months agocb4a6c4
1 year, 7 months agoJaya12
1 year, 8 months ago