A project lead is managing a project in the execution phase. A new product owner was assigned and the project lead had their first meeting with the new product owner. During the meeting, the new product owner indicated the scope of the first release needs to be changed.
What should the project lead ask the product owner to do first?
STAR666
3 months agovictory108
6 months ago517f9da
1 year agoAbdelmonm
1 year, 4 months agoodylec
1 year, 4 months ago6thEditionAndy
1 year, 5 months agocb4a6c4
1 year, 5 months agocertificate988
1 year, 5 months agoJaya12
1 year, 5 months ago