A project team has identified a risk and wants to accept it as an opportunity to finish a project earlier than planned. The project manager realizes that the sponsor may not accept the risk since the sponsor is risk averse.
What should the project manager do?
UppersquareCapital
Highly Voted 1 year, 4 months agovictory108
Most Recent 7 months, 1 week agoKim222
9 months agodatntcn3
10 months, 3 weeks agosidje
1 year agoUppersquareCapital
1 year, 2 months agoYUCHAN2022
1 year, 3 months agoTrytrio
1 year, 3 months agoSAJSAJ
1 year, 3 months agoAbdelmonm
1 year, 4 months agoAbdelmonm
1 year, 4 months agoJaya12
1 year, 5 months agocb4a6c4
1 year, 5 months agocertificate988
1 year, 6 months ago