A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule.
What should be the project manager’s response?
kaarenn
5 months, 3 weeks agovictory108
6 months agoc8ee0e6
9 months, 3 weeks agoUppersquareCapital
11 months, 1 week agolatigo
11 months, 2 weeks agosidje
11 months, 2 weeks agoompk
11 months, 3 weeks agoAzureFreak
1 year, 1 month agodimo475
1 year, 1 month agoEfaChux
1 year, 1 month agoDavard
1 year, 2 months agoKennyMuffins
1 year, 2 months agoTrytrio
1 year, 2 months agoDelab202
1 year, 3 months agoAbdelmonm
1 year, 3 months agoced45c8
1 year, 3 months agokevzzz
1 year, 3 months ago