A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule.
What should be the project manager’s response?
certificate988
Highly Voted 1 year, 7 months agokaarenn
Most Recent 7 months, 4 weeks ago8a6d137
2 weeks agovictory108
8 months, 1 week agoc8ee0e6
11 months, 3 weeks agoUppersquareCapital
1 year, 1 month ago8a6d137
2 weeks agolatigo
1 year, 1 month agosidje
1 year, 1 month agoompk
1 year, 1 month agoAzureFreak
1 year, 3 months agodimo475
1 year, 3 months agoEfaChux
1 year, 3 months agoDavard
1 year, 4 months agoKennyMuffins
1 year, 5 months agoTrytrio
1 year, 5 months agoDelab202
1 year, 5 months ago8a6d137
2 weeks agoAbdelmonm
1 year, 5 months agoced45c8
1 year, 5 months ago