A project manager is using a hybrid approach for a project. The project team created and reviewed the risk log with the stakeholders at the beginning of the project. However, midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies.
When should the risks be reviewed to ensure alignment between the project team and the stakeholders?
3c59785
1 month, 2 weeks agovictory108
7 months, 3 weeks agod370e49
9 months, 2 weeks agoompk
1 year, 1 month agosidje
1 year, 1 month agoAbdelmonm
1 year, 5 months agochlaithem
1 year, 5 months agoamali999
1 year, 6 months agoJaya12
1 year, 6 months agoMaMana
1 year, 6 months agoElla008
1 year, 6 months agogsap
1 year, 6 months agoHanbyul
1 year, 6 months ago