A project has completed the first phase. During the lessons learned meeting, the project manager reported that the project was successful because it was on time, on budget, and on scope. The sponsor objected and said that other project benefits, such as cost reduction of the product and system response time, were not achieved.
What may have caused this situation?
certificate988
Highly Voted 1 year, 6 months agovictory108
Most Recent 6 months, 2 weeks agoUppersquareCapital
1 year ago517f9da
1 year agoTrytrio
1 year, 4 months agojosephsafiran
1 year, 4 months agoUppersquareCapital
1 year, 4 months agoUppersquareCapital
1 year, 4 months agoAbdelmonm
1 year, 4 months agomesacgon
1 year, 5 months agoodylec
1 year, 5 months agoElla008
1 year, 5 months agocb4a6c4
1 year, 6 months ago