A project manager is executing a commercial building project. The project manager discovers that the required building permits have not been obtained. Obtaining the permits will delay the project by 1 month and will cost the project US$35,000. The fine associated with continuing to build without the permits is US$1,000 per day.
What should the project manager do first?
cb4a6c4
Highly Voted 1 year, 6 months agonicknamesdx
1 year agovictory108
Most Recent 6 months, 2 weeks agoNgho
8 months agoKim222
10 months ago517f9da
1 year agoTrytrio
1 year, 4 months agoAbdelmonm
1 year, 4 months agomesacgon
1 year, 4 months agochlaithem
1 year, 4 months agoxcjxcj
1 year, 5 months agoced45c8
1 year, 5 months ago6thEditionAndy
1 year, 6 months agoJaya12
1 year, 6 months agocertificate988
1 year, 6 months ago