A project manager finds a mistake with an important server acquisition. The acquisition was expected for a critical path activity but has not arrived yet, causing significant impacts on time and cost. The team member responsible for this activity argues that they sent several emails to the supplier but received no reply.
Which document should be used to help avoid this kind of situation?
victory108
6 months, 3 weeks agosidje
1 year agoompk
1 year agoKim222
9 months, 2 weeks agoiuedeme
1 year, 1 month agoYUCHAN2022
1 year, 3 months agoTrytrio
1 year, 3 months agoAbdelmonm
1 year, 4 months agoDelab202
1 year, 4 months agoDelab202
1 year, 4 months agokevzzz
1 year, 4 months agopsvexam
1 year, 4 months agoxcjxcj
1 year, 4 months agoDivya_Naidu
1 year, 5 months agoJaya12
1 year, 5 months ago6thEditionAndy
1 year, 5 months agonewnewuser
1 year, 5 months ago