A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor is very keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.
How should the project manager address this situation?
Anssoo
2 months, 4 weeks ago8a6d137
1 month, 2 weeks agovictory108
8 months, 2 weeks agoKim222
11 months, 1 week agoKim222
12 months agoKim222
11 months, 1 week ago517f9da
1 year, 2 months agohoomz
1 year, 5 months agoTrytrio
1 year, 6 months agoUppersquareCapital
1 year, 6 months agoced45c8
1 year, 7 months agoamali999
1 year, 7 months ago6thEditionAndy
1 year, 7 months agoJaya12
1 year, 8 months agocb4a6c4
1 year, 8 months ago