exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1002 discussion

Actual exam question from PMI's PMP
Question #: 1002
Topic #: 1
[All PMP Questions]

A project manager is assigned to a project. There was a lot of conflict regarding the status of the project and compliance with international regulations. During a regular meeting, the sponsor wanted to know how frequently the risks are being reviewed.

Which document project manager should check first?

  • A. Risk management plan
  • B. Risk register
  • C. Issue log
  • D. Risk report
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Sarvesh_D
9 months, 1 week ago
Risk management plan is not a document .... last line messed up
upvoted 1 times
...
victory108
9 months, 2 weeks ago
Selected Answer: A
A. Risk management plan
upvoted 1 times
...
517f9da
1 year, 2 months ago
Selected Answer: A
A. Risk management plan The risk management plan includes information on how often risks should be reviewed, along with methodologies, roles, and responsibilities.
upvoted 2 times
...
PeterCK
1 year, 3 months ago
Selected Answer: A
Risk management plan should include everything you need.
upvoted 2 times
...
kevzzz
1 year, 5 months ago
Selected Answer: A
A risk management plan defines how your project's risk management process will be executed. That includes the budget, tools and approaches that will be used to perform risk identification, assessment, mitigation and monitoring activities.
upvoted 1 times
...
hoomz
1 year, 5 months ago
Selected Answer: A
They key word is "How"
upvoted 2 times
...
vrj021819
1 year, 5 months ago
A. Risk mgmt pan
upvoted 1 times
...
Trytrio
1 year, 6 months ago
Selected Answer: A
In this situation, where the project sponsor wants to know how frequently the risks are being reviewed, the project manager should check the Risk Management Plan (Option A) first. This document outlines how risk management processes will be conducted throughout the project, including the frequency of risk reviews. The Risk Management Plan provides the framework and guidelines for all risk-related activities, making it the appropriate first reference in this scenario.
upvoted 1 times
...
KennyMuffins
1 year, 6 months ago
Selected Answer: A
Risk register contains risks.
upvoted 1 times
...
psvexam
1 year, 7 months ago
Ans A. As per definition, Risk register is just a record of all risks, mitigation strategies etc. But Risk management plan is the document which defines how and frequency of communication etc. But in reality, anybody would refer to Risk register.
upvoted 2 times
...
6thEditionAndy
1 year, 7 months ago
Selected Answer: A
The risk management plam outlines how risks are analysed, including the frequency
upvoted 3 times
...
Jaya12
1 year, 7 months ago
Selected Answer: B
By referring to the Risk Register, the project manager can accurately convey to the sponsor the frequency of risk assessments and reviews for the project, ensuring effective risk management practices in line with PMBOK principles.
upvoted 2 times
...
cb4a6c4
1 year, 8 months ago
Selected Answer: B
Risk Management plan details the approach of handling risk, risk register is the place its updated, analyzed and actioned.
upvoted 2 times
cb4a6c4
1 year, 7 months ago
Sorry its A. Process for identifying, analyzing, responding to, and monitoring risks are part of risk management plan. Risk register only shows the current state not the frequency. Any thougts?
upvoted 4 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...