At a daily standup on the second day of the sprint, the product owner asks one of the developers to add more functionality to a product backlog item that was committed to in the sprint planning. The product owner explains that the change is based on a discussion they had with a user, is critical, and should be delivered in the next release.
What should the project manager do?
victory108
8 months, 1 week agoKim222
10 months, 2 weeks agoKim222
9 months, 3 weeks ago517f9da
1 year, 1 month agokevzzz
1 year, 3 months agoCommonNickname
1 year, 4 months agovrj021819
1 year, 4 months agohoomz
1 year, 4 months agoTrytrio
1 year, 4 months ago58e5964
1 year, 5 months agoAbdelmonm
1 year, 5 months agochlaithem
1 year, 5 months agoAntoFE
1 year, 5 months agoamali999
1 year, 5 months agoWaynelau
1 year, 6 months ago6thEditionAndy
1 year, 6 months agoJaya12
1 year, 6 months agosblivia
1 year, 6 months ago