exam questions

Exam PgMP All Questions

View all questions & answers for the PgMP exam

Exam PgMP topic 1 question 309 discussion

Actual exam question from PMI's PgMP
Question #: 309
Topic #: 1
[All PgMP Questions]

A program manager has four projects pending approval. Senior management asks the program manager to identify a project for potential elimination based on the return on investment. The program manager has the following information to guide and support the decision:

Which project should the program manager select to be cancelled?

  • A. Project A
  • B. Project B
  • C. Project C
  • D. Project D
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
hanyulin
10 months, 1 week ago
Selected Answer: D
Sorry, the question is about ROI,the answer should be D
upvoted 1 times
...
happykaur
10 months, 2 weeks ago
Selected Answer: D
ROI of A is -22% and D is -33%.
upvoted 1 times
...
[Removed]
11 months, 1 week ago
Selected Answer: D
ROI A= 7/9 ROI D = 2/3=6/9 Project D should be cancelled
upvoted 1 times
...
hanyulin
11 months, 3 weeks ago
Selected Answer: A
It's should be A
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...