Question #: 883
Topic #: 1
[All PMP Questions]

A project manager has been newly assigned to an existing project. The project manager noted that the input from a business unit, which is critical to the success of the project, was not included in any project assets. Instead, there were many complaints about the project's operational results and the alignment with solutions affected by the business unit's operations.

What action should the project manager take?

  • A. Validate that the project requirements information is up-to-date.
  • B. Determine the degree to which the project is in compliance.
  • C. Optimize alignment among needs, expectations, and project objectives.
  • D. Determine a strategy for change responses to new objective requests.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Abdelmonm
9 months, 2 weeks ago
Selected Answer: C
The project manager should focus on optimizing alignment among needs, expectations, and project objectives. In this situation, it's crucial to ensure that the project is aligned with the needs and expectations of the business unit that is critical to the project's success. This may involve engaging with the business unit, understanding their requirements, and making necessary adjustments to the project to better align with their operations and objectives. Simply validating requirements, determining compliance, and strategizing for change responses may not address the root issue of alignment with the critical business unit.
upvoted 2 times
...
cb4a6c4
10 months, 4 weeks ago
Selected Answer: C
Optimizing alignment involves the project team and stakeholders who can address the concerns and work towards business success.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.