Question #: 887
Topic #: 1
[All PMP Questions]

A company is looking to adopt a new software solution to align business processes across multiple business units using a technology that was never used in the organization. What should the project manager focus on?

  • A. New system and the likelihood of technical debt
  • B. Specific requirements for important departments
  • C. Out-of-scope requirements across the organization
  • D. Conflicting priorities and business requirements
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
PeterCK
2 weeks, 6 days ago
ChatGPT answer is A lolz
upvoted 1 times
...
Rick_nkp
2 months ago
The project manager should focus on identifying and addressing potential technical debt that may arise from implementing a new technology. This involves evaluating the capabilities of the new system and assessing the potential impact on the organization's existing infrastructure and processes.
upvoted 1 times
...
Trytrio
3 months ago
Selected Answer: D
In summary, while option B focuses on specific requirements for key departments, option D takes a more holistic view of the organization, recognizing the potential for conflicting priorities and business requirements across multiple units. Both considerations are essential, but option D encompasses a broader perspective and highlights the need for overall alignment and resolution of conflicts, making it a more comprehensive approach in this context.
upvoted 1 times
...
josephsafiran
3 months, 1 week ago
Selected Answer: D
The project manager should focus on Option D: Conflicting priorities and business requirements. When implementing a new software solution across multiple business units, especially with a technology that’s new to the organization, it’s crucial to manage and reconcile conflicting priorities and requirements.
upvoted 1 times
...
chlaithem
3 months, 3 weeks ago
Selected Answer: D
Rationale for focusing on conflicting priorities and business requirements: Aligning diverse needs: Implementing a new system across multiple business units with potentially contrasting needs and priorities is the biggest challenge. Understanding and reconciling these differences is crucial for a successful implementation. Managing expectations: Aligning business requirements with technical feasibility and budget constraints while navigating conflicting priorities requires proactive communication and managing stakeholder expectations. Ensuring long-term success: Focusing solely on specific departmental needs or technical aspects might neglect the bigger picture of aligning the system with overarching business goals and potential conflicts between units. B. Specific requirements for important departments: While understanding departmental needs is essential, addressing conflicting priorities across departments takes precedence to ensure overall system alignment and avoid future issues.
upvoted 1 times
...
UppersquareCapital
3 months, 3 weeks ago
Selected Answer: B
B. Specific requirements for important departments. Understanding the specific requirements of the important departments involved is crucial for the successful adoption of the new software solution. This includes gathering detailed requirements from each business unit to ensure that the chosen technology can effectively meet their needs and align with their processes. This approach helps in tailoring the implementation to the unique requirements of each department, increasing the chances of successful adoption and alignment across the organization.
upvoted 1 times
...
odylec
4 months, 1 week ago
Selected Answer: D
Must be D. If you focus on the importans dpts you lose the half company. You must not forget what happens out of company
upvoted 1 times
...
cb4a6c4
4 months, 2 weeks ago
B seems the the right answer. Understand the requirement for all departments and work on specific requirements from important departments. Any suggestions?
upvoted 1 times
AntoFE
4 months ago
Be would have risks! Berceuse it only focus on the requirement of the important departments.
upvoted 1 times
...
...
cb4a6c4
4 months, 3 weeks ago
Selected Answer: D
Its D. Focusing on few important department may lead to overlook the requirements of others there by not providing a balanced solution.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...