You are planning to set up a regular portfolio oversight meeting. How do you ensure stakeholder communication requirements are met?

  • A. Use a dashboard to increase transparency
  • B. Ensure the meeting is aligned with the communication management plan
  • C. Engage stakeholders to ensure their needs are met
  • D. Ensure stakeholders available to join the meeting
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
nihenu
1 year ago
Selected Answer: B
SPfM 7.1.3.1 The portfolio communication management plan defines all communication needs, establishes communication requirements, specifies frequency, and identifies recipients for information associated with the portfolio management processes.
upvoted 1 times
...
dnskanakov
1 year ago
Selected Answer: B
stakeholder requirements are mentioned in Communications Management plan
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted