Question #: 11
Topic #: 1
[All PfMP Questions]

Which of the following should be included in a portfolio risk management plan? (Choose two.)

  • A. Dependencies
  • B. Methodology
  • C. Roles and responsibilities
  • D. Key milestones and deliverables
Show Suggested Answer Hide Answer
Suggested Answer: BC 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
70a60ed
2 weeks, 5 days ago
Selected Answer: BC
8.1.3.1 3rd Ed.
upvoted 1 times
...
dnskanakov
1 year, 2 months ago
correct, secion 8.1.3.1 3rd Edition
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...