Exam PgMP topic 1 question 381 discussion

Actual exam question from PMI's PgMP
Question #: 381
Topic #: 1
[All PgMP Questions]

A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits.
Which of the following actions should the program manager take?

  • A. Focus on the internal stakeholders to ensure cost and schedule objectives are achieved.
  • B. Balance stakeholder needs through the use of trade-offs among the stakeholder groups.
  • C. Focus on the external stakeholders to ensure the intended benefits are achieved.
  • D. Conduct a stakeholder meeting to allow everyone to state their priorities.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tungdt
10 months, 2 weeks ago
B is correct
upvoted 1 times
...
happykaur
1 year, 4 months ago
Selected Answer: B
In this scenario, where there are conflicting stakeholder demands related to cost, schedule, and benefits, the program manager should: B. Balance stakeholder needs through the use of trade-offs among the stakeholder groups. This approach ensures that the program manager addresses the diverse and possibly conflicting interests of different stakeholders. It involves negotiating and finding an acceptable compromise that aligns with the program's overall objectives, rather than focusing solely on one group's interests. This balance is crucial for the success and sustainability of the program.
upvoted 1 times
...
[Removed]
1 year, 5 months ago
Selected Answer: B
B. Balance stakeholder needs through the use of trade-offs among the stakeholder groups. Program management often involves managing competing stakeholder demands. A balanced approach that considers the different priorities of internal and external stakeholders is crucial. The program manager must find a way to deliver the program within the constraints of cost and schedule while also ensuring that the intended benefits, which are of primary concern to the client, are realized. This may involve trade-offs and compromises to meet the most critical objectives of each stakeholder group as effectively as possible.
upvoted 1 times
...
hanyulin
1 year, 5 months ago
Selected Answer: B
B is the right answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.