Question #: 60
Topic #: 1
[All PfMP Questions]

During a governance meeting, a functional manager introduced a new collaboration software to improve communication. You learned that this software could raise the effectiveness of portfolio communication management. Which item should you update to capture this founding?

  • A. Organizational process assets
  • B. Portfolio communication management plan
  • C. Enterprise environmental factors
  • D. Portfolio process assets
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
dnskanakov
1 year, 1 month ago
Selected Answer: B
The most appropriate item to update to capture the introduction of the new collaboration software that could enhance portfolio communication management would be: B. Portfolio communication management plan The Portfolio Communication Management Plan outlines strategies, methods, and tools used for communication within the portfolio. Updating this plan to incorporate the new collaboration software ensures that the portfolio's communication strategies reflect the latest tools and technologies available to enhance communication effectiveness.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...