A project manager held a meeting and framed the project schedule. A critical stakeholder, who was not consulted at the time of the schedule discussion, complained that the published dates are not agreeable due to a prescheduled task for another assignment.
What should the project manager do first?
deviszont
Highly Voted 1 year, 5 months agovictory108
Most Recent 7 months agoKim222
9 months, 2 weeks agoc8ee0e6
10 months, 2 weeks agoPmpjune152024
11 months, 2 weeks agoompk
12 months agodimo475
1 year, 2 months agoKennyMuffins
1 year, 2 months agoPeterCK
1 year, 1 month agohoomz
1 year, 3 months agoDavard
1 year, 3 months agoAbdelmonm
1 year, 4 months agoJaya12
1 year, 5 months ago