A project manager held a meeting and framed the project schedule. A critical stakeholder, who was not consulted at the time of the schedule discussion, complained that the published dates are not agreeable due to a prescheduled task for another assignment.
What should the project manager do first?
deviszont
Highly Voted 1 year, 7 months agovictory108
Most Recent 8 months, 3 weeks agoKim222
11 months, 1 week agoc8ee0e6
1 year agoPmpjune152024
1 year, 1 month agoompk
1 year, 1 month agodimo475
1 year, 4 months agoKennyMuffins
1 year, 4 months agoPeterCK
1 year, 3 months agohoomz
1 year, 4 months agoDavard
1 year, 5 months agoAbdelmonm
1 year, 6 months agoJaya12
1 year, 7 months ago