A project manager held a meeting and framed the project schedule. A critical stakeholder, who was not consulted at the time of the schedule discussion, complained that the published dates are not agreeable due to a prescheduled task for another assignment.
What should the project manager do first?
deviszont
Highly Voted 4 months, 3 weeks agodimo475
Most Recent 1 month, 2 weeks agoKennyMuffins
2 months, 1 week agoPeterCK
2 weeks, 5 days agohoomz
2 months, 2 weeks agoDavard
3 months, 1 week agoAbdelmonm
3 months, 4 weeks agoJaya12
4 months, 3 weeks ago