Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PMP topic 1 question 1091 discussion

Actual exam question from PMI's PMP
Question #: 1091
Topic #: 1
[All PMP Questions]

A project manager held a meeting and framed the project schedule. A critical stakeholder, who was not consulted at the time of the schedule discussion, complained that the published dates are not agreeable due to a prescheduled task for another assignment.

What should the project manager do first?

  • A. Organize a new schedule framing meeting with the critical stakeholder to obtain input.
  • B. Discuss with the project sponsor and create a new project schedule.
  • C. Analyze the root cause of the issue and update the communications management plan.
  • D. Reach out to the project sponsor and request additional resources.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
deviszont
Highly Voted 4 months, 3 weeks ago
Selected Answer: C
If we are taling about the FIRST step the PM needs to take: from my perspective it has to be investigated why a critical stakeholder was not consulted and this issue has to be corrected. Then the second step the PM needs to take: he/she needs to organize new schedule framing meeting with the critical stakeholder.
upvoted 7 times
...
dimo475
Most Recent 1 month, 2 weeks ago
C Those kinds of questions are without meaning. They dont offer knowledge. I say C but I think that it's a meaningless question.
upvoted 1 times
...
KennyMuffins
2 months, 1 week ago
Selected Answer: A
Question states "do first" = immediate proactive action to resolve the situation. Rather than RCA, engaging the stakeholder is the most immediate action to take to resolve the issue at hand.
upvoted 2 times
PeterCK
2 weeks, 5 days ago
Agree, both A and C should be do by this situation. but A should "Do First" then C later.
upvoted 1 times
...
...
hoomz
2 months, 2 weeks ago
Selected Answer: A
While a proactive measure for the future, understanding the root cause doesn't immediately fix the scheduling clash and further delays resolution.
upvoted 1 times
...
Davard
3 months, 1 week ago
Selected Answer: A
Analyzing the root cause of the issue and updating the communications management plan (option C) may be relevant for addressing communication gaps or issues, but the immediate priority is to address the stakeholder's concerns regarding the project schedule.
upvoted 4 times
...
Abdelmonm
3 months, 4 weeks ago
Selected Answer: A
By involving the critical stakeholder in a new schedule framing meeting, the project manager can gather their input and considerations, ensuring that their schedule constraints and commitments are taken into account. This promotes collaboration and helps in creating a more realistic and feasible project schedule.
upvoted 2 times
...
Jaya12
4 months, 3 weeks ago
Selected Answer: C
This approach involves investigating why the critical stakeholder was not consulted during the schedule framing meeting. Understanding and rectifying this root cause will help prevent similar oversights in the future, improving stakeholder engagement practices.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...