D is the best answer
If a program manager is concerned that a program will be unable to achieve its intended benefits, the most appropriate course of action would be to:
D. Meet with the component project managers to perform risk analysis.
Performing a risk analysis with the component project managers will help identify and assess the risks that could be impacting the program's ability to achieve its benefits. This will allow the program manager to develop and implement mitigation strategies to address these risks and improve the likelihood of achieving the intended benefits.
A. Meet with the program management office (PMO) to review critical program success factors.
Meeting with the PMO to review critical program success factors allows the program manager to take a holistic view of the program's health and progress. The PMO can provide insights, guidance, and support in evaluating the overall program strategy, goals, and alignment with organizational objectives. This review can help in identifying the root causes of the concern regarding the achievement of benefits and in determining the necessary steps to realign the program for success.
This section is not available anymore. Please use the main Exam Page.PgMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
tungdt
1 year ago[Removed]
1 year, 7 months agohanyulin
1 year, 7 months ago