Which of the following is NOT true regarding the program work breakdown structure (WBS)?

  • A. It defines a program and groups the program's discrete work elements in a way that helps organize and define the total work scope of the program.
  • B. It subdivides the program deliverables to work packages that are linked to the activities within the program.
  • C. It defines all the work and only the required work for the program.
  • D. It subdivides the program deliverables to work packages that are linked to the activities within the program.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
[Removed]
10 months, 3 weeks ago
D=B. Maybe a wrong option written
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago