exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 276 discussion

Actual exam question from PMI's CAPM
Question #: 276
Topic #: 1
[All CAPM Questions]

What process in Project Schedule Management identifies and documents specific actions to be performed to produce a project’s deliverables?

  • A. Plan Schedule Management
  • B. Define Activities
  • C. Develop Schedule
  • D. Estimate Activity Durations
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: B
Key phrases: "identifies and documents specific actions to be performed" = activities
upvoted 1 times
...
JesseChou_123
1 month, 3 weeks ago
Selected Answer: B
Why not the others? A. Plan Schedule Management → This defines how the schedule will be managed, not what activities will be performed. C. Develop Schedule → This process sequences activities, assigns durations, and creates the schedule model — after activities are defined. D. Estimate Activity Durations → This determines how long each activity will take — after they've been defined.
upvoted 1 times
...
041ba31
1 year, 1 month ago
B. Define Activities The process in Project Schedule Management that identifies and documents specific actions to be performed to produce a project's deliverables is "Define Activities." In this process, the project manager and team break down the work packages or higher-level activities into smaller, manageable tasks or activities. These activities are then documented and defined in a way that makes them clear and actionable. This is an important step in developing the project schedule because it lays the foundation for further scheduling activities, such as sequencing and estimating durations, which are part of the overall schedule development process.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...