Exam CAPM topic 1 question 272 discussion

Actual exam question from PMI's CAPM
Question #: 272
Topic #: 1
[All CAPM Questions]

Which of the following is an output of the Perform Integrated Change Control process?

  • A. Cost-benefit analysis
  • B. Updated project charter
  • C. Approved change request
  • D. Multicriteria decision analysis
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 2 weeks ago
Selected Answer: C
Change Control = Change Request
upvoted 1 times
...
041ba31
1 year, 1 month ago
C. Approved change request The output of the Perform Integrated Change Control process is typically an "Approved change request." This process involves reviewing and making decisions about proposed changes to the project, and if a change is approved, it becomes an approved change request that can then be implemented by the project team. The other options (A. Cost-benefit analysis, B. Updated project charter, D. Multicriteria decision analysis) are tools and techniques or inputs used in the Perform Integrated Change Control process but are not the primary output of the process.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...