Product requirements specify a functionality that depends upon expertise that is unavailable internally. What process should be implemented to generate a make-or-buy decision?
B. Plan Procurement Management
When product requirements specify a functionality that depends on expertise that is unavailable internally and a decision needs to be made regarding whether to make the product in-house or buy it from an external source, the appropriate process to implement is "Plan Procurement Management."
In this process, the project team evaluates the various procurement options, including make-or-buy decisions. It involves determining whether it's more advantageous to procure the required expertise externally through contracts or to develop it internally. The process helps in defining the procurement strategy, identifying potential sellers, and establishing the criteria for selecting the right approach, which includes the make-or-buy decision.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
041ba31
10 months, 3 weeks ago