Question #: 263
Topic #: 1
[All CAPM Questions]

How does planning for prevention costs assist in meeting stakeholder needs and expectations, while still providing required performance and reliability?

  • A. It details product or service failures experienced by the customer
  • B. It clarifies the costs associated with assessing the quality of the product or service
  • C. It accounts for costs used to avoid poor quality in the product or service
  • D. It communicates product or service failures discovered by the project team
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
2 weeks, 1 day ago
Selected Answer: C
Why not the others? A. This refers to external failure costs (issues found by the customer), not prevention. B. This describes appraisal costs, which are for inspecting and testing, not preventing. D. This is related to internal failure costs, when the project team finds defects before delivery. Thus, C best aligns with the role of planning prevention costs in delivering quality outcomes.
upvoted 1 times
...
041ba31
1 year ago
C. It accounts for costs used to avoid poor quality in the product or service Planning for prevention costs involves allocating resources and efforts to activities and processes that are aimed at avoiding poor quality in the product or service. This proactive approach focuses on identifying and preventing defects and issues before they occur. By investing in prevention, a project or organization can ensure that the product or service meets or exceeds stakeholder needs and expectations while providing the required performance and reliability. Option C is the correct choice because it accurately describes how planning for prevention costs helps in meeting stakeholder needs and expectations by avoiding quality problems and ensuring that the product or service is of high quality from the outset.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...