A project manager is addressing risks and potential concerns related to stakeholder management, and is clarifying and resolving previously identified issues. In which process is the project manager engaged?
Why not the others?
A. Identify Stakeholders: Focuses on determining who stakeholders are and analyzing their influence and interest.
B. Plan Stakeholder Engagement: Involves developing strategies for engaging stakeholders.
D. Monitor Stakeholder Engagement: Focuses on tracking stakeholder relationships and adjusting strategies accordingly.
C. Manage Stakeholder Engagement
When a project manager is addressing risks and potential concerns related to stakeholder management, as well as clarifying and resolving previously identified issues, they are typically engaged in the "Manage Stakeholder Engagement" process. This process involves actively managing stakeholder expectations, addressing stakeholder concerns and issues, and ensuring effective communication and engagement throughout the project. It focuses on keeping stakeholders informed and satisfied to maximize their support for the project's success.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
1 month, 2 weeks ago041ba31