A project manager is in charge of a software development project. A key stakeholder complains that they never received the functionality test status reports. The project manager provides the reports, and the stakeholder notices that an important functionality for their area was not tested.
Which tool should the project manager have used to prevent this situation?
Nimitto
5 months, 1 week agovictory108
6 months, 2 weeks ago27b2ada
8 months agoKim222
8 months, 1 week agoc8ee0e6
9 months, 4 weeks agoLNX_RM_Admin
11 months, 3 weeks ago[Removed]
1 year, 2 months agommhawish
1 year, 3 months agoTrytrio
1 year, 3 months agodinodragon
10 months, 3 weeks agoKennyMuffins
1 year, 3 months agoDavard
1 year, 3 months agomesacgon
1 year, 3 months agoDelab202
1 year, 3 months agoMoyWH
1 year, 4 months agoAbdelmonm
1 year, 4 months agogsap
1 year, 4 months ago