A biometrics firm has a facial recognition program with multiple components and project managers. The project manager from the mobile device division escalates a vendor-related risk to the program manager. After assessing the risk, the program manager determines that this risk may impact other projects within the program. However, this risk has a low degree of impact and probability of occurring.
What should the program manager do first?