Most risks are assessed for probability and impact. Which of the following are other factors that should be considered?

  • A. Urgency and complexity
  • B. Manageability and cost
  • C. Urgency and manageability
  • D. Manageability and complexity
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AKB968
1 year, 1 month ago
Complexity is no parameter for assess risks,,, so C is answer, urgnecy and managibility
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.