The project manager of a project in trouble actively participates in a project risk assessment. After the assessment is complete, the project manager receives the final results.
What is the best recommended action to be taken from this point onward?

  • A. Schedule a meeting and present the assessment results.
  • B. Use the assessment results in the day-to-day management of project risks.
  • C. Schedule a meeting with the project sponsor and discuss the assessment results.
  • D. Use the assessment results to review the project hand over plan to operations.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AKB968
1 year, 1 month ago
B is the answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...