A program manager, who reports to a company's CIO, is responsible for managing a strategic initiative program. During a program review meeting, the CIO informs the program manager about potential budget cuts that would impact program resources, and urges the program manager to begin delivering benefits more quickly to continue the program.
What should the program manager do first?

  • A. Update the benefits management plan, and send it to stakeholders for review.
  • B. Document the impact on the program, then present the findings to the steering committee to determine next steps.
  • C. Conduct a risk assessment associated with an accelerated schedule, update the risk register, and request steering committee approval.
  • D. Revise the program schedule to adapt to an accelerated delivery of benefits, and present it to the steering committee for approval.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
hanyulin
1 year, 1 month ago
Selected Answer: C
C is the right answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...