Exam PgMP topic 1 question 412 discussion

Actual exam question from PMI's PgMP
Question #: 412
Topic #: 1
[All PgMP Questions]

A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks.
What should the program manager do next to address this risk?

  • A. Prioritize which resources are critical to the project based on an impact analysis of the critical change requests and update the program roadmap.
  • B. Prioritize which change requests are critical to the project based on an impact analysis, resource only critical change requests until overdue milestones are achieved, and update the risk register.
  • C. Mandate that no component project change requests will be processed until overdue milestones have been completed and update the risk register to reflect this.
  • D. Add the lack of skilled resources to facilitate the large number of change requests to the issue log.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
hanyulin
1 year, 1 month ago
Selected Answer: B
B is the right answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...