exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 13 discussion

Actual exam question from PMI's PMI-RMP
Question #: 13
Topic #: 1
[All PMI-RMP Questions]

The risk manager wants to determine what is to be measured, how it is to be measured, and what project outcomes are to be measured. In which of the following processes should this be established?

  • A. Initiating Process
  • B. Executing Process
  • C. Planning Process
  • D. Monitoring and Controlling Process
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
_MCV_
11 months, 1 week ago
This is part of the Methodology included in the Risk Management Plan. Correct answer is C
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...