A multi-year complex program will deliver advanced driver assistance system (ADAS) components for autonomous vehicles. Several key stakeholders are concerned because they have not been regularly involved with the program and do not understand the program's benefits.
What should the program manager do to address these key stakeholders' concerns?

  • A. Meet with the stakeholders and update the stakeholder map.
  • B. Create a progress report to share with stakeholders after the next status meeting.
  • C. Capture stakeholder expectations, and revise the stakeholder engagement plan.
  • D. Update the communications management plan after meeting with the program steering committee.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tungdt
10 months, 2 weeks ago
C is correct
upvoted 1 times
...
happykaur
1 year, 4 months ago
Selected Answer: C
A multi-year complex program will deliver advanced driver assistance system (ADAS) components for autonomous vehicles. Several key stakeholders are concerned because they have not been regularly involved with the program and do not understand the program's benefits. What should the program manager do to address these key stakeholders' concerns? A. Meet with the stakeholders and update the stakeholder map. B. Create a progress report to share with stakeholders after the next status meeting. C. Capture stakeholder expectations, and revise the stakeholder engagement plan. D. Update the communications management plan after meeting with the program steering committee.
upvoted 1 times
...
[Removed]
1 year, 5 months ago
Selected Answer: C
C. Capture stakeholder expectations, and revise the stakeholder engagement plan. In this situation, where key stakeholders are concerned about their lack of involvement and understanding of the program's benefits, the program manager should actively engage with these stakeholders to capture their expectations and concerns. Following this, the program manager should revise the stakeholder engagement plan to address these concerns. This plan is a strategic document that outlines how stakeholders will be engaged and communicated with throughout the program. By revising this plan to include more regular and targeted engagement activities for the concerned stakeholders, the program manager can ensure that they are kept informed and their needs are addressed. This approach not only alleviates their concerns but also helps in gaining their support and buy-in for the program.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...