A company is starting a new agile project with a team that has expertise working on these kinds of projects. During the backlog refinement meeting, the team realizes that they are not completing the estimations because some key information is missing.
What should the project manager do?
victory108
8 months, 1 week ago23169fd
8 months, 3 weeks agoc8ee0e6
11 months, 4 weeks agoNadirJT
1 year, 2 months agoDelab202
1 year, 5 months agoAbdelmonm
1 year, 5 months agokevzzz
1 year, 6 months agoKim222
10 months agopsvexam
1 year, 6 months ago