A project manager is executing a large project with many stakeholders. One of the primary stakeholders is requesting a change to the project scope. The project manager knows that this scope change will not require much effort from the project team. The project manager is worried that going through the full change control process will hold up the project schedule.
What should the project manager do?
victory108
8 months, 3 weeks agoKim222
11 months, 1 week ago517f9da
1 year, 2 months agoAbdelmonm
1 year, 6 months agopsvexam
1 year, 7 months ago8a6d137
1 month, 2 weeks ago