A project team is transitioning to agile delivery. The team uses a Kanban board to track progress. In the daily meetings, the team members have been reporting good progress. However, the cards on the board are not progressing toward "done."
What should the project manager do?
victory108
6 months, 2 weeks ago517f9da
1 year agohoomz
1 year, 3 months agoTrytrio
1 year, 4 months agoKennyMuffins
1 year, 4 months agojosephsafiran
1 year, 4 months ago58e5964
1 year, 4 months agoUppersquareCapital
1 year, 4 months agoAbdelmonm
1 year, 4 months agoAbdelmonm
1 year, 4 months agoAbdelmonm
1 year, 4 months agoodylec
1 year, 5 months ago