A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee:
• Actual progress = 2 units
• Planned progress = 3 units
• Actual cost (AC) = 2 units
• Budgeted cost = 3 units
What statement should the project manager make to the project steering committee?
victory108
7 months, 1 week agoAbdelmonm
1 year, 4 months agoAbdelmonm
1 year, 4 months ago