exam questions

Exam PgMP All Questions

View all questions & answers for the PgMP exam

Exam PgMP topic 1 question 393 discussion

Actual exam question from PMI's PgMP
Question #: 393
Topic #: 1
[All PgMP Questions]

Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.
What should be done with the identified potential risk?

  • A. Incorporate it into the risk register and perform a thorough analysis.
  • B. Mitigate the risk before it is incorporated into the risk management plan.
  • C. Document the risk in the program transition plan and identify it as a potential issue.
  • D. Document it in the issue log and immediately notify the steering committee.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
hanyulin
10 months, 2 weeks ago
Selected Answer: A
A is right answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...