Exam PMP topic 1 question 967 discussion

Actual exam question from PMI's PMP
Question #: 967
Topic #: 1
[All PMP Questions]

In the initial project meeting, a stakeholder presents a complaint about the validity of the project. The complaint occurs after the stakeholder discovers that the project will not deliver the objectives they expected and will have a higher cost.

How should the project manager handle the complaint?

  • A. Highlight the reasons for the project cost increase and negotiate with the providers to reduce the cost.
  • B. Use management skills to convince the stakeholder in agreeing to the project cost.
  • C. Delay discussions with the stakeholder and request a revision of the project with the sponsors.
  • D. Reinforce the importance of the project mission and the overall vision of the work to be performed.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
6 months, 2 weeks ago
Selected Answer: D
D. Reinforce the importance of the project mission and the overall vision of the work to be performed
upvoted 1 times
...
517f9da
1 year ago
Selected Answer: D
D. Reinforce the importance of the project mission and the overall vision of the work to be performed. Reinforcing the importance of the project mission and the overall vision helps the stakeholder understand the broader objectives and value of the project. This approach can help address concerns by focusing on the project's strategic alignment and benefits, potentially mitigating the stakeholder's dissatisfaction with the specific objectives and costs.
upvoted 1 times
...
hoomz
1 year, 3 months ago
Selected Answer: C
D likely to be ineffective if the stakeholder feels the project, as currently defined, doesn't meet their needs.
upvoted 1 times
...
Abdelmonm
1 year, 4 months ago
Selected Answer: D
In handling the stakeholder's complaint, reinforcing the importance of the project mission and the overall vision helps to align the stakeholder with the broader objectives and goals of the project. It can provide context for the project decisions and changes, emphasizing the value and purpose behind them. This approach aims to address concerns by focusing on the strategic aspects of the project, potentially mitigating dissatisfaction and fostering a better understanding of the project's direction and benefits.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...