A pharmacy needs to launch a medication delivery service. An interdisciplinary team was created in order to have the service ready in one-month when it usually takes five months to complete.
What should the project manager do?
A.
Register a risk and define a contingency plan.
B.
Review and reduce the project backlog.
C.
Assist the team in proposing a minimum viable product (MVP).
C. Assist the team in proposing a minimum viable product (MVP).
Given the tight timeframe and the need to launch the medication delivery service in one month instead of the usual five months, focusing on a Minimum Viable Product (MVP) is a practical and effective approach. The project manager should work with the interdisciplinary team to identify the essential features and functionalities required for the initial launch. The MVP approach allows the team to prioritize and deliver the most critical components within the limited timeframe, ensuring that the core service is functional and can be released on time. This approach aligns with agile principles and facilitates a quicker time-to-market.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
UppersquareCapital
10 months, 2 weeks ago