A project team member identifies, but does not document, a risk early in the project, because it is considered to be trivial. This risk occurs later and negatively impacts the project. What could the project manager do to avoid this situation?
A.
Conduct team meetings early in the project to ensure team member are familiar with risk identification requirements.
B.
Communicate the punishment and rewards policy to the project team during the project kick-off meeting.
C.
Provide project team members with access to simulation tools and decision tree diagrams.
D.
Provide team members with a risk management prompt list early in the project to ensure risks are not missed.
This section is not available anymore. Please use the main Exam Page.PMI-RMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Loan
10 months, 2 weeks ago