The risk manager completes risk response planning. The risk manager believes that to effectively address all eventualities, an additional action is required. What should the program manager do next?
In this scenario, after the risk manager completes risk response planning and believes additional action is required to address all eventualities, the most appropriate next step for the program manager would be:
B. **Establish a contingency reserve.**
Establishing a contingency reserve is a proactive step to prepare for uncertainties in project management. It involves setting aside resources (such as time, money, or manpower) to address potential risks that may materialize during the course of the project. This reserve acts as a buffer to manage risks that were not completely eliminated or mitigated during the risk planning phase.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PgMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
happykaur
10 months, 2 weeks ago