A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls, and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project, which could impact other components if delays occur. The program manager's attempts to reach the stakeholder via email also fail.
What should the program manager do next?

  • A. Escalate the issue to the stakeholder's supervisor
  • B. Escalate the issue to the program governance board, as delays will impact the program
  • C. Update the program risk register to reflect a realized risk and execute the documented risk response
  • D. Attempt to call the key stakeholder; if unsuccessful, visit their office to identify potential risks
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tungdt
10 months, 2 weeks ago
B is the best answer. there is no standard "stakeholder's supervisor" in Program of PMI.
upvoted 1 times
...
happykaur
1 year, 4 months ago
Selected Answer: A
In this scenario, where a key stakeholder is unresponsive and this behavior could potentially impact the program, the next step for the program manager should be: A. Escalate the issue to the stakeholder's supervisor. Escalation to the stakeholder's supervisor is a direct and appropriate approach to address the lack of response. It allows for involvement from a higher authority who may have more influence over the stakeholder, potentially leading to a resolution. Given the stakeholder's significant influence and the potential impact on the program, it's important to address this issue promptly and effectively at the appropriate level of authority within the stakeholder's organization. This approach also demonstrates proactive management and escalation of issues that could adversely affect the program's progress.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...