exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 987 discussion

Actual exam question from PMI's PMP
Question #: 987
Topic #: 1
[All PMP Questions]

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing project. Based on that information, the project manager believes the project should be stopped.

How should the project manager handle the situation?

  • A. Have a discussion with the project sponsor and cancel the project.
  • B. Remove the items no longer applicable from the backlog and present the backlog to the project team.
  • C. Continue working on the defined scope and review the risk matrix.
  • D. Have a discussion with the sponsor and recommend the project business value be reassessed.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
6 months, 2 weeks ago
Selected Answer: D
D. Have a discussion with the sponsor and recommend the project business value be reassessed
upvoted 1 times
...
517f9da
1 year ago
Selected Answer: D
Very logical D. Have a discussion with the sponsor and recommend the project business value be reassessed. Explanation: Reassessing the project's business value with the sponsor ensures that informed decisions are made based on the latest information. This approach allows for evaluating the project's viability and making necessary adjustments to align with current market conditions.
upvoted 1 times
...
UppersquareCapital
1 year, 4 months ago
Selected Answer: D
In this situation, the project manager should communicate with the project sponsor to discuss the newly acquired market information and its potential impact on the project's business value. It's essential to recommend a reassessment of the project business value based on the updated information.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...