Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PMP topic 1 question 1134 discussion

Actual exam question from PMI's PMP
Question #: 1134
Topic #: 1
[All PMP Questions]

One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests that this might just be a small task.

What should the project manager do?

  • A. Perform a qualitative risk analysis.
  • B. Coordinate design document preparation.
  • C. Request further clarification of the requirement.
  • D. Manage the engagement of this stakeholder.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
PeterCK
2 weeks, 3 days ago
Selected Answer: C
Analysis first
upvoted 1 times
...
Nathan4real21
3 months, 1 week ago
Selected Answer: C
Any change must go through an impact analysis
upvoted 1 times
...
Victory007
3 months, 2 weeks ago
Selected Answer: C
Before making any decisions that could impact the project, it’s important to fully understand the new requirement. This includes its scope, its impact on the project’s objectives, and why it’s being requested. Once the project manager has this information, they can assess the situation accurately and make an informed decision.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...